Current major projects
Project Type Area Description Details Current Status
Neighborhood Upgrades
Thurston – North of Main Street Underground cable replacement and transformer relocation B Street to Thurston Road from 66th Street to 69th Street Design at 75%
73rd Street Electric upgrade project and transformer relocation A Street to B Street from 72nd Place to 73rd Place Complete
Kathryn Ave, 35th to 39th Streets Proactive replacement of aging overhead infrastructure Pole and wire replacement Complete
South of Centennial/Aspen Underground cable replacement and transformer relocation Rainbow Ave to Prescott Lane, from Janus Street to Granite Place Design at 95%
Hayden Bridge Rd, 28th to 31st Proactive replacement of aging overhead infrastructure Pole replacement Design at 90%
Royal Delle Park Proactive replacement of aging overhead infrastructure Pole and wire replacement, Blackstone St to Cambridge St Design at 90%
Olympic & 42nd Street Proactive replacement of aging overhead infrastructure Pole replacement, Construction at 20%
System Upgrades
Thurston Natural Area Rebuild feeder East Springfield Complete
Springfield Substation Expand substation to support Rosboro expansion 18th/South A Distribution at 40% construction
Rosboro Install feeders from Springfield Substation to Rosboro South A from South 16th St to South 23rd Contractor conduit, Fall 2026
Glenwood Substation Construction overview Glenwood Substation Construction Design complete; Construction at 80%
Glenwood 115kv transmission line Extend existing transmission line Along I-5 to Glenwood Substation In approval. Construction planned for late 2026
Glenwood 20.8 kV distribution Underground and overhead feeder construction From Glenwood Substation west along E 22nd Ave, to Henderson, then north to 19th Ave. Construction at 90%