Bid Number: 2021-31
Bid Due: 10/05/2021 2:00 pm
Bid Status: Closed
Prevailing Wage Required: Yes
Bid Questions Contact: Rebecca Wheeler
Bid Questions Email: rebeccaw@subutil.com
Bid Questions Phone: 541-726-2396
Technical Questions Contact: Steven Wages Cell
Technical Questions Email: stevenw@subutil.com
Technical Questions Phone Number: 541-525-4113


Documents

SECTION 00 01 16
INVITATION TO BID
FOR
WILLAMETTE SSFP SAND MEDIA PLACEMENT
SUB PROJECT NO. 21381
BID NO. 2021 – 31
FOR
SPRINGFIELD UTILITY BOARD

2021_31_WIL SSFP Sand Media Placement Bid Document.pdf

2021_31_Addendum Numb1

2021_31_Addendum Numb2

Due to COVID-19 restrictions, Electronic proposals for Willamette SSFP Sand Media Placement project will be accepted. To submit electronically, please email Rebecca Wheeler at rebeccaw@subutil.com. Email must be received no later than 2 p.m., Pacific Standard Time, on Tuesday, October 5th, 2021 to be accepted. The options for sealed, hardcopy proposal packet delivery are as follows:
Mail to: Rebecca Wheeler, Water Division, Springfield Utility Board, 202 South 18th Street, Springfield, OR 97477; or, drop off at the above address during business hours, then proceed by calling the front desk at 541-726-2396 to make aware of the delivery. No bids will be received after the BID CLOSING time.

A MANDATORY PRE-BID MEETING for this project will be held at the project Site, located at 1295 South 26th Street, Springfield, Oregon 97477 on the Thursday, September 30th, 2021 at 10:00 AM to provide prospective bidders with the opportunity to ask questions relating to bidding or constructing the work under this contract and to acquaint Bidders with the Site conditions. If deemed appropriate by the Engineer, questions that cannot be addressed by direct reference to the bidding documents will be the subject of an addendum. A BIDDER’S FAILURE TO ATTEND THE PRE-BID MEETING SHALL CAUSE ANY BID SUBMITTED BY THAT BIDDER TO BE DEEMED NON-RESPONSIVE AND THE BID WILL BE RETURNED UNOPENED.

Contemplated work consists of furnishing all labor and equipment necessary for the following work:

A. Flipping the old and new sand through the trench method shown in Detail 1 on
C-1. This method is use in order to not place undue equipment pressures on the existing filter bed.
B. Excavate and dispose of the dirty sand from edges of the liner of the Filter Bed #3 at SUB designated area (take extra care not to damage liner, any damage SUB will back charge the contractor to have a certified liner contractor repair).
C. Removing approximately 14-Inches of existing sand from the bottom of the filter in trench/rows (leave 4-inchs of existing sand in place to avoid the gravel media under the sand).
D. Installing approximately 18-Inches of new sand from the sand storage area.
E. Cap the new sand with a 14-Inch layer of the removed existing sand.
F. The top of the sand layer must be a uniform density and elevation so that the filter cleaning machine can operate on the surface.
G. The top of the finished media shall be flat to within a tolerance of plus or minus 0.04 feet of the average elevation.
H. Steel Tracks equipment is not allowed within the filter bed area due to the bed liner system.
I. All equipment shall be steam cleaned and leak free prior to being mobilized onsite.
J. Equipment needs food grade fluids for the hydraulics, coolant, grease, to access filter beds for placement of the sand media (preferred products BioFlo HEES 46, AMSOIL Propylene Glycol, TruGrease FG AP 2 or prior engineered approval).

Note: This work is Prevailing Wage as determined by BOLI.

A complete set of proposal documents may be viewed in PDF format and downloaded at https://www.subutil.com/bids-proposals/
No proposal will be considered by the Springfield Utility Board unless the Bidder agrees to be bound by and will comply with the provisions of ORS 279C.800 to 279C.870 and 40 U.S.C. 276(a) pertaining to prevailing wages, as applicable. Each bid must contain a statement as to whether or not the bidder is a resident bidder as defined in ORS 279A.120. Each bid must also contain a statement as to whether the bidder is registered with the Oregon Construction Contractors Board. No bid will be received or considered unless the bidder is registered with the Construction Contractors Board, as required by ORS 701.035.ET.SEQ. Faxed copies will NOT be accepted.

Special minimum experience qualifications apply to portions of this project. General Contractors (Bidders) who are not already listed as pre-qualified by the Engineer shall submit to the Engineer a Request for Qualification complying in form and content to the requirements of the bid documents. The minimum qualifications and submittal requirements are specified in the Contract Documents. Requests for Qualification shall be presented to Engineer no later than 5 p.m., Pacific Standard Time, on 28th of September, 2021. All Requests for Qualification shall be sent directly to Steven Wages, P.E., Springfield Utility Board, 202 S 18th Street, Springfield, OR 97477, phone 541-744-3728. PROPOSALS SUBMITTED BY A NON-QUALIFIED GENERAL CONTRACTOR (BIDDER) SHALL BE CONSIDERED NON-RESPONSIVE AND SHALL BE REJECTED. First-tier and other subcontractors must be accepted by Springfield Utility Board prior to the pre-construction meeting.

Proposals must be submitted on the prescribed forms. The successful bidder will be required to furnish to Springfield Utility Board a performance bond and a payment bond each equal to one hundred percent (100%) of the amount of the bid. The successful bidder and all subcontractors will be required to furnish to the Oregon Construction Contractors Board a public works bond in the amount of $30,000, unless exempt under ORS 279C.

Acceptance of bids and award of contract will follow procedures provided by ORS 279C and in accordance with all applicable Springfield Utility Board policies. Springfield Utility Board reserves the right to reject any and all bids, to waive any irregularities, and to accept the bid deemed in the best interests of Springfield Utility Board. Springfield Utility Board may reject any bid not in compliance with all prescribed public bidding procedures and requirements, and may reject for good cause any or all bids upon a finding of the agency it is in the public interest to do so.

Dated this 24th day of September, 2021
By: Steven Wages P.E., Civil Engineer, Springfield Utility Board


Mandatory Pre-Bid Conference

These are tentative bid results pending Board approval and sand delivery.  This will serve as our intent to award.

Contractor Total Price
Big River Construction, Inc. $109,998.00
Emery & Sons Construction Group, Inc. $136,444.00